甲公司生产急需5000个零件,承包给乙工厂进行加工,每个零件的加工费预算为20元,计划2周(每周工作5
A.该项目的费用偏差为-18000元
B.该项目的进度偏差为-18000元
C.该项目的CPI为0.80
D.该项目的SPI为0.90
A.该项目的费用偏差为-18000元
B.该项目的进度偏差为-18000元
C.该项目的CPI为0.80
D.该项目的SPI为0.90
问题:
(1)本案中谁应受理此案?
(2)双方在纠纷发生后达成的书面仲裁协议是否成立?为什么?
(3)如果乙公司提出仲裁协议无效,应由谁来裁定,如何审查?
A.network interface layer, internet layer, transport layer and application layer
B.internet layer, network interface layer, transport layer and application layer
C.network interface layer, transport layer, network interface layer and application layer
D.application layer, transport layer, internet layer and network interface layer
A.Cost-Benefit analysis
B.Control charts
C.Quality function deployment
D.Cost of quality analysis
A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
A. ERP软件强调事后核算,而财务软件强调及时调整
B.财务软件强调事后核算,ERP软件强调事前计划和及时调整
C. ERP软件强调事后核算,而进销存软件比较关注每种产品的成本构成
D.进销存软件强调事后核算,财务软件强调及时调整
A.计算机网络系统的安装调试
B..计算机应用系统的部署和实施
C..计算机信息系统的设计、研发、实施和服务
D.计算机应用系统工程和网络系统工程的总体策划、设计、开发、实施、服务及保障
A.两个或者多个信息系统之间相互访问数据资源
B.企业海量数据的存储和访问
C.企业决策信息的挖掘和提取
D.不同地域的企业信息系统之间进行实时的信息共享和数据通信
A.数据文件、应用数据库、主题数据库、信息检索数据库
B.数据文件、主题数据库、应用数据库、数据仓库
C.元数据库、主题数据库、应用数据库、数据仓库
D.元数据库、应用数据库、主题数据库、信息检索数据库
为了保护您的账号安全,请在“简答题”公众号进行验证,点击“官网服务”-“账号验证”后输入验证码“”完成验证,验证成功后方可继续查看答案!