As a project communication management process, administrative closeout consists of verify
A.Project archives, formal acceptance, and lessons learned
B.Change requests, project records, and lessons learned
C.Lessons learned, performance reports, and change requests
D.Communication management plans, change requests, and project archives
E.None of the above