11 When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.
A. Reduce features and/or functionality
B Increase risk.
C. Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)
D. All of the above.
E. A and B only