[单选题]
()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.A.Identity risksB.Control risksC.Plan risk responsesD.Plan risk management
A.Identity risks
B.Control risks
C.Plan risk responses
D.Plan risk management