The Cost Performance Index (CPI) measuresA.total costsB.performance over a period of timeC
The Cost Performance Index (CPI) measures
A.total costs
B.performance over a period of time
C.costs at a point of time
D.variable costs
E.All of the above.
The Cost Performance Index (CPI) measures
A.total costs
B.performance over a period of time
C.costs at a point of time
D.variable costs
E.All of the above.
110 The Cost Performance Index (CPI) measures
A. total costs
B. performance over a period of time
C. costs at a point of time
D. variable costs
E. All of the above
45 The most common definition of project success is:
A. Within time
B. Within time and cost
C. Within time, cost and technical performance requirements
D. Within time, cost, performance and accepted by the customer/user
E. None of the above
A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
14 Using the situation stated in the Special window, what is the cost performance index for Case #9? A. 1.10
B. 1.91
C. 0.83
D. 1.20
E. None of the above
A post project evaluation
B post contract evaluation
C post mortem
D procurement performance evaluation
E contractor's performance evaluation
A、only responsiveness
B、only cost performance
C、both responsiveness and cost performance
D、responsiveness, but not cost performance
A、Schedule varlance (SV)
B、Cost varlance (CV)
C、Actual cost (AC)
D、Earned value (EV)
158 The computation for Cost Performance Index is:
A. BCWP/ACWP
B. BCWP-ACWP
C. BCWP-BCWS
D. ACWP/BCWP
E. ACWP-BCWS