148A project manager believes that modifying the scope of the project may provide added va
148 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:
A. Change the scope baseline
B. Prepare a variance report
C. Call a meeting of the configuration control board
D. Change the project's objectives
E. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline