An element in the WBS was estimated to require 1 month for completion with 1000 hours of l
abor and a burdened cost of $50K. The task was completed in 1000 hours but a burdened cost of $60K. The most likely reason for the increase would be:
A . Higher salaried employees were assigned.
B . Overtime was required.
C . The overhead rate increased.
D . Employee salaries had increased.
E . Any of the above