某项目经理所在的单位正在启动一个新的项目,配备了虚拟项目小组。根据过去的经验,该项目经理认识到矩阵环境下的小组成员有时对职能经理的配合超过对项目经理的配合。因此,该项目经理决定请求单位制定(27)。在项目执行过程中,有时需要对项目的范围进行变更,(28)属于项目范围变更。
A.项目计划
B.项目章程
C.项目范围说明书
D.人力资源管理计划
- · 有4位网友选择 D,占比40%
- · 有3位网友选择 C,占比30%
- · 有2位网友选择 B,占比20%
- · 有1位网友选择 A,占比10%
A.项目计划
B.项目章程
C.项目范围说明书
D.人力资源管理计划
A.Controls
B.Baselines
C.Project stakeholders
D.Project managers
A.PDM
B.CPM
C.PERT
D.AOA
Estimating schedule activity costs involves developing an(69)of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estimates are generally expressed in units of(70)to facilitate comparisons both within and across projects.The(71 )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost estimating.
A.accuracy
B.approximation
C.specification
D.summary
A.设定模型、检验模型、估计模型、改进模型
B.设定模型、估计参数、检验模型、应用模型
C.估计模型、应用模型、检验模型、改进模型
D.搜集资料、设定模型、估计参数、应用模型
A.项目日常开支的速度和生产率
B.项目日常开支的速度和工期拖延
C.项目补贴和加班
D.原材料成本和运输成本
A.逐步交付
B.顺序
C.循环
D.增量
A.PERT网络分析
B.甘特图
C.优先日程图法
D.启发式分析法
A.软件需求
B.软件分析
C.软件设计
D.软件实现
A.analysis phase
B.design phase
C.implementation phase
D.maintenance phase
A.责任分配矩阵(RAM)被用来表示需要完成的工作和团队成员之间的联系
B.项目经理或项目管理团队应该积极参与到人力资源的行政管理工作中去
C.组织分解结构(OBS)根据项目的交付物进行分解,因此团队成员能够了解应提供哪些交付物
D.项目经理和职能经理应协商确保项目所需的员工按时到岗,并完成所分配的项目任务
为了保护您的账号安全,请在“简答题”公众号进行验证,点击“官网服务”-“账号验证”后输入验证码“”完成验证,验证成功后方可继续查看答案!