154A Work Breakdown Structure: A.assures all work is identified B.subdivides the project i
154 A Work Breakdown Structure:
A. assures all work is identified
B. subdivides the project into manageable segments
C. provides the project sponsor with a time-phase task summary
D. both A and B
E. All of the above