Project Risk _____ .Ashould not be calculated for small projects.Bis the probability of ea
Project Risk _____ .
A should not be calculated for small projects.
B is the probability of each risk event minus the sum of the consequences of potential risk events.
C is the cumulative effect of uncertain occurrences which will adversely affect project objectives.
D cannot be quantified for first time projects.
E B or D