You are the project manager for a large government contract.The contract was signed a year
A.Tell the sponsor and your senior management that any changes are out of scope at this point and cannot be considere
B.Meet with the project sponsor and senior management to discuss this problem and potential solutions.
C.Talk to your legal department to make sure you doesn’t do anything illegal.
D.Ask senor management to set aside more management reserve to avoid potential financial problems.