Standard deviation of project completion is _____ .Aa relationship of the uncertainty of c
Standard deviation of project completion is _____ .
A a relationship of the uncertainty of critical path activities.
B an indicator of project end date target confidence
C a function of critical path, leveling and project costs.
D A and B
E All of the above.