搜题
网友您好,请在下方输入框内输入要搜索的题目:
搜题
题目内容 (请给出正确答案)
提问人:网友wuqipanyifei 发布时间:2022-01-07
[主观题]

After a baseline check was completed it was noted that the network was working far below t

helevel of the last baseline.Which of the following should the technician do NEXT to determine where the network problems are occurring?()

A. Upgrade the firmware on all routers and switches

B. Reboot the entire network one device at a time

C. Conduct a network traffic analysis

D. Rerun the baseline to ensure the results were correct

简答题官方参考答案 (由简答题聘请的专业题库老师提供的解答)
查看官方参考答案
更多“After a baseline check was completed it was noted that the network was working far below t”相关的问题
第1题
A project manager believes that modifying the scope of the project may provide added value
for the customer. The project manager should:

A.Change the scope baseline

B.Prepare a variance report

C.Call a meeting of the configuration control board

D.Change the project's objectives

E.Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

点击查看答案
第2题
● A project manager believes that modifying the scope of the project may provide added val
ue service for the customer. The project manager should(75).

(75)

A.assign change tasks to project members

B.call a meeting of the configuration control board

C.change the scope baseline

D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

点击查看答案
第3题
● A project manager believes that modifying the scope of the project may provide added val
ue service for the customer .The project manager should()()A. assign change tasks to project membersB. call a meeting of the configuration control boardC. change the scope baselineD. postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

点击查看答案
第4题
148A project manager believes that modifying the scope of the project may provide added va

148 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:

A. Change the scope baseline

B. Prepare a variance report

C. Call a meeting of the configuration control board

D. Change the project's objectives

E. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

点击查看答案
第5题
66A project manager believes that modifying the scope of the project may provide added val

66 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:

A. Change the scope baseline

B. Prepare a variance report

C. Call a meeting of the configuration control board

D. Change the project's objectives

E. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

点击查看答案
第6题
The following command is executed to create the baseline template:Which statement is true about the effect of the above command?()

A. It creates a baseline template that never expires.

B. It produces an error because no snapshot information is provided to create the baseline.

C. It creates a baseline template that expires after the Automatic Workload Repository (AWR) retention period.

D. It creates a repeating baseline template that repeats after the Automatic Workload Repository (AWR) retention period.

点击查看答案
第7题
156During project execution, the customer authorizes and funds a scope change which requir

156 During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:

A. Now becomes the new schedule, including the changes, and the original baseline is disregarded. B. Is still the original baseline but annotated to reflect that a change has taken place.

C. Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.

D. Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)

E. Is the same since baseline schedules cannot change once the development phase is completed

点击查看答案
第8题
38During project execution, the customer authorizes and funds a scope change which require

38 During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:

A. Now becomes the new schedule, including the changes, and the original baseline is disregarded. B. Is still the original baseline but annotated to reflect that a change has taken place.

C. Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.

D. Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)

E. Is the same since baseline schedules cannot change once the development phase is completed

点击查看答案
重要提示: 请勿将账号共享给其他人使用,违者账号将被封禁!
查看《购买须知》>>>
重置密码
账号:
旧密码:
新密码:
确认密码:
确认修改
购买搜题卡查看答案
购买前请仔细阅读《购买须知》
请选择支付方式
微信支付
支付宝支付
点击支付即表示你同意并接受《服务协议》《购买须知》
立即支付
搜题卡使用说明

1. 搜题次数扣减规则:

功能 扣减规则
基础费
(查看答案)
加收费
(AI功能)
文字搜题、查看答案 1/每题 0/每次
语音搜题、查看答案 1/每题 2/每次
单题拍照识别、查看答案 1/每题 2/每次
整页拍照识别、查看答案 1/每题 5/每次

备注:网站、APP、小程序均支持文字搜题、查看答案;语音搜题、单题拍照识别、整页拍照识别仅APP、小程序支持。

2. 使用语音搜索、拍照搜索等AI功能需安装APP(或打开微信小程序)。

3. 搜题卡过期将作废,不支持退款,请在有效期内使用完毕。

请使用微信扫码支付(元)

订单号:

遇到问题请联系在线客服

请不要关闭本页面,支付完成后请点击【支付完成】按钮
遇到问题请联系在线客服
恭喜您,购买搜题卡成功 系统为您生成的账号密码如下:
重要提示:请勿将账号共享给其他人使用,违者账号将被封禁。
发送账号到微信 保存账号查看答案
怕账号密码记不住?建议关注微信公众号绑定微信,开通微信扫码登录功能
警告:系统检测到您的账号存在安全风险

为了保护您的账号安全,请在“简答题”公众号进行验证,点击“官网服务”-“账号验证”后输入验证码“”完成验证,验证成功后方可继续查看答案!

- 微信扫码关注简答题 -
警告:系统检测到您的账号存在安全风险
抱歉,您的账号因涉嫌违反简答题购买须知被冻结。您可在“简答题”微信公众号中的“官网服务”-“账号解封申请”申请解封,或联系客服
- 微信扫码关注简答题 -
请用微信扫码测试
欢迎分享答案

为鼓励登录用户提交答案,简答题每个月将会抽取一批参与作答的用户给予奖励,具体奖励活动请关注官方微信公众号:简答题

简答题官方微信公众号

简答题
下载APP
关注公众号
TOP