156During project execution, the customer authorizes and funds a scope change which requir
156 During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:
A. Now becomes the new schedule, including the changes, and the original baseline is disregarded. B. Is still the original baseline but annotated to reflect that a change has taken place.
C. Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.
D. Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)
E. Is the same since baseline schedules cannot change once the development phase is completed