One Class Surveyor got onboard of a 45000 DWT new construction Chemical Tanker a week befo
re delivery, he carried out the initial Safety Equipment survey in accordance with the Fire Fighting and Life-saving Control Plan.Surveyor noted that the vessel had two ()
A.The surveyor’s comment was not correct; because the Life-raft has the Hydra-Static Releaser, should not care the height of Storing Position
B.The surveyor’s comment was correct; because if the Storing height was over the Limit of the Life-raft, It may damage the Life-raft when throwing off to the water
C.The surveyor’s comment was not correct; the storing position was the same location as showing on the approved drawings
D.The surveyor’s comment was correct; as a surveyor, he can give any comment as he like